News

Now onto the good bit…..

Hydro base emerging from the river bed; screw on order

Great news of the last couple of weeks is that we have stopped digging and started building! The photographs below show the base for the microhydro growing out of the riverbed and we can already see the distinctive curved end of the Powerhouse beautifully cast in concrete.

This means that we are moving swiftly towards the end of the hydro civils with the changeover to the Environment Agency Weir B works taking place seamlessly in the next week or two. Doing Osney Lock Hydro’s work followed by Environment Agency maintenance and repair to Weirs B and A minimises disruption and means that all the work to the Lock and surrounding weirs is done in one go.

We will be able to move on to the most exciting part of the project, to install the generator, early in the New Year. The Environment Agency will follow on from hydro/Weir B civils to do repairs and replacements to the hand radials at Weir A between mid-October and Christmas.

This week we have also placed the order for the Archimedes screw that will generate the power at Osney Lock Hydro. It takes a minimum of four months’ lead-in time for the order to be built and delivered from Holland.

A very good late development is that we have decided to have a variable-speed screw built. This has two very important advantages for Osney Lock Hydro: firstly, it means that the screw will be able to turn more slowly when the river levels are low and therefore operate more efficiently and even more quietly than we were expecting; secondly, it means that the energy in the head of water can be converted to power more efficiently, thereby increasing generation by 15-20%.

Site Photos 230813 001 reduced Site Photos 230813 002 reduced Site Photos 230813 003 reduced Site Photo 160813 0004

Revealing the secrets of the river bed

Crane in the sunset . Photo credit - David Jeffrey

Crane in the sunset . Photo credit – David Jeffrey

With the cofferdam in place, water has now been drained from the site of Weir B, so work on the riverbed can commence. The draining of the site also provides a unique opportunity to learn more about its history. A key point of interest is the century old winding gear for the weir.

Oxford Archeology have been commissioned to document the findings, and we are investigating how we might combine the old winding gear into our new design as a way of showcasing and preserving this fascinating piece of waterways history.

In the meantime, we are hearing reports that our crane is proving of interest to residents of all ages – from young toddlers, to the young at heart. Thank you to David Jeffrey for sharing his photo of the crane at dusk.

Building work starts

Construction of the cofferdam started on Monday 8th July. In consultation with the Environment Agency, our contractors have slightly modified the design of the cofferdam. As a result the contractor has implemented a special piling head which as enabled them to use a relatively quiet piling technique using a ‘silent hammer’ or vibro-hammer. We have completed the cofferdam using this technique, however for the rest of the piling we may still need to switch to impact piling depending on ground conditions encountered.

photo2_lowres photo1_lowress (800x600)

Construction Work Begins at Osney Lock

Osney Lock Hydro and the Environment Agency are pleased to announce that the Osney Lock site has now been fully mobilised and so construction work can begin on building the generator base for the Hydro and replacing the Weir B gates.

The first element of the work is to build cofferdams to keep the water out of the working area. These are put in both upstream and downstream of the site and are built by driving interlocking steel sheet piles into the riverbed. The upstream coffer dam will need to be removed if we have a period of heavy rain to let the floodwaters through the existing Weir B gates. This is normal practice and a flow monitoring and action protocol is in place should river flows increase significantly from normal.

Cofferdam construction latest

We are dismayed to be once again announcing a further week’s delay to the start of pile driving on the site.

The delay continues to be due to the finalising of the details relating to the leasing of the site. We had a very constructive meeting with the Environment Agency’s legal team today, and expect preparatory works to commence next week, with pile driving itself now due to start on Monday 8th July.

Cofferdam construction start date

Cofferdam construction
One of the first tasks for the contractors will be to put in a cofferdam, to enable the civil engineering works to take place. It is anticipated that the pile-driving will take around two weeks (10 working days) at the time of writing is now expected to start the week commencing 1st July.

The coffer dam is needed for both the hydro’s civil engineering work and the Environment Agency’s work on Weir B. The weir at the site of the hydro and this maintenance work has been planned for some time.

Site preparation starts

As part of the preparation of the site, the Himalayan Cedar at Osney Lock was felled today along with a small crab apple tree and some shrubs. This followed a visit by our ecologist to check the site for nesting birds. There were no nests in the felled tree, but the sycamore and conifer trees will be left for a further 14 days because they do contain nests.

The work begins

And we’re off! The first consignment of kit arriving on site. We’ll be bringing you regular updates on our progress via the website. Look out for updates in the news section as well via a new ‘construction’ area which will be going live shortly.

The kit rolling in

The kit rolling in

 

Osney Lock Hydro and Fish

We have been disappointed by recent inaccurate stories in the local press regarding the impact of hydro schemes on fish, for example, a piece in last week’s Oxford Times Anglers warn over Thames hydro-plant threat to fish.’ We have felt particularly dismayed given the care we have taken to fully assess the ecological impact of our scheme and in our choice of hydro technology, and of course this information was included in our application for planning permission.